Most Altadena rebuilds can't start framing until there's power on the lot, and that means a temporary power pole. Altadena is unincorporated LA County on Southern California Edison (SCE), so two agencies are involved: LA County Public Works issues the electrical permit and inspects the pole, and SCE sets the meter and energizes it. The pole is quick to build. The paperwork is what slows things down. Here's the SCE and County sequence for Eaton Fire rebuilds as of November 2026, and how to plan temporary power so it doesn't cost you on the permanent service later. Ready to get power on your lot? Request a free estimate or call 747-255-8595.

Who Does What on an Altadena Temporary Power Job

  • SCE reviews the service request, confirms where the service can connect, and sends a crew to set the meter once the County releases the job.
  • LA County Public Works (Building and Safety) issues the electrical permit for the temporary pole and inspects it.
  • Your C-10 electrician files the SCE request, pulls the permit, builds and sets the pole, and books the inspection.

One check first: look at an old electric bill. Most of Altadena is on SCE, but parts of the Eaton Fire area are inside the City of Pasadena and on Pasadena Water and Power (PWP), with City of Pasadena permits. Those steps are different.

Step 1: Get Your SCE Application ID

LA County's Eaton Fire agency referral sheet says an Application Identification Number from SCE is required for all rebuilds, new ADUs, new panels and temporary power. You apply online through SCE's project portal. Treat this as the first step, because the County permit and SCE's planning both hang on it.

SCE runs a dedicated disaster recovery line at 1-800-250-7339 (Monday to Friday 7 a.m. to 7 p.m., Saturday 8 a.m. to 5 p.m.). For in-person help, SCE's Altadena Rebuild & Community Hub (ARCH) at 2680 Fair Oaks Ave. handles service planning, temporary power, panel upgrades and undergrounding questions, according to SCE's Altadena FAQ (updated Oct 16, 2026).

Step 2: The LA County Temporary Power Permit

SCE says customers must apply for a County permit to authorize the temporary pole. We pull it under our C-10 license through LA County's EPIC-LA portal, with the parcel information and a site plan showing where the pole goes.

The permit itself is not the big cost. Under LA County's electrical fee schedule effective July 1, 2026, the County charges $65.36 per temporary service power pole or pedestal, plus a $41.35 permit issuing fee. Plan for the pole, materials and labor on top of that. For in-person permit help, the Altadena One-Stop Permit Center is at 464 W. Woodbury Rd., Suite 210, (626) 424-6743. Walk-ins are Monday to Friday, 8 a.m. to 4:30 p.m., with a 3 p.m. last call for permits, and the County lists virtual SCE planner appointments on Monday and Wednesday mornings.

Step 3: Build the Pole, Pass Inspection, Get the Release

Once SCE has confirmed the service location and the permit is issued, we set the pole: a braced post with the meter socket, a small panel, GFCI-protected weatherproof outlets and grounding. Our temporary power pole guide covers the typical specs.

Then the County inspects. SCE's process for Altadena is straightforward: the County inspects the temporary power installation and sends an inspection release to SCE. Once SCE receives the release, it sends a crew to set the meter and energize the pole. SCE doesn't publish a fixed wait for that last step, so we track the release and follow up with SCE rather than promise a date.

What usually causes delays: no clear address on a cleared lot, a pole placed somewhere SCE didn't approve, or a failed inspection on grounding or GFCI protection. Get those right and the job moves.

Plan for Underground Service Now

SCE is undergrounding much of Altadena's electric system in phases, and its FAQ says there's no single date by neighborhood. That affects your rebuild even while you're on a temporary pole:

  • A home can be built with underground conduit now and served overhead temporarily until permanent underground service is ready.
  • A combo panel that accepts both overhead and underground service supports that switch later.
  • If civil work is already underway, SCE says installing trenching and conduit during the rebuild helps prepare for underground service. Confirm the route with your SCE planner first.

On cost, SCE says it doesn't charge rebuilding customers a reconnection fee and customers don't pay for SCE's work to connect the home. Trenching, conduit and panel work on your side of the property line are generally the owner's cost. When you're ready for the permanent service, our Altadena rebuild and panel upgrade guide and new construction electrical page pick up from there. Going all-electric? See our Altadena SWITCH rebates guide.

Frequently Asked Questions

How do I get temporary power for my Altadena rebuild?

Submit a service request to SCE, get a County permit for the temporary pole, have the pole built and inspected, and SCE sets the meter after the County sends its inspection release.

Do I need an SCE Application ID for a temporary power pole?

Yes. LA County's Eaton Fire referral sheet says an SCE Application Identification Number is required for temporary power, as well as for rebuilds, new ADUs and new panels.

How much is the LA County permit for a temporary power pole?

As of the fee schedule effective July 1, 2026, LA County charges $65.36 per temporary pole or pedestal plus a $41.35 permit issuing fee. The pole and installation are separate.

Who energizes the temporary pole?

SCE. After LA County inspects the pole and sends the inspection release, SCE sends a crew to set the meter and turn the power on.

Can I build for underground service while on temporary overhead power?

Yes. SCE says a home can be built with underground conduit now and served overhead temporarily, and a combo panel can support both.

Need Temporary Power for Your Altadena Rebuild? Call a Licensed C-10

911 Construction & Electric Inc. is a licensed, bonded and insured C-10 electrical contractor (CA Lic. #1027421) at 1308 E Colorado Blvd Ste 141, Pasadena, CA 91106, serving Altadena, Pasadena, Sierra Madre, the San Gabriel Valley and greater Los Angeles. We handle SCE service requests, LA County permits, temporary power poles, inspections and permanent rebuild service for homes in Altadena and across SCE territory. Request a free estimate, call 747-255-8595 or visit https://911electrics.com. 24/7 emergency service available.